NH 24 Widening 14 Lane Work Progress Status, Completion Date | Delhi-UP Date-Dasna-Hapur | Delhi Meerut Expressway

National Highway 24 Delhi, Ghaziabad, Dasna, Hapur, Meerut Six Lane Expressway in middle, Eight Lane Normal Highway, 2.5 Meter Bicycle Track on both side, widening work on this corridor was started in May 2016. Prime Minister Shri Narendra Modi ji was laid the foundation stone of this widening project on 31st Dec 2015 in Noida Sector 62 Stadium. The construction project of widening NH 24 from 4 Lane to 14 Lanes continues postponed from past 10 years, but finally widening work in progress.

National Highway 24 is the lifeline of Ghaziabad, when this project is complete it will help Noida, Greater Noida and Delhi residential & commercial project like Wave City, Crossing Republik, Gaur City Greater Noida West, Eco Village etc.

Delhi Meerut Expressway 6 Lane | NH 24 Widening Delhi To UP Gate To Dasna 14 Lanes | NH 9 Dasna To Hapur 8 Lane | Work Completion Deadline Date December 2020 Set By PM MODI JI

NH 24 Widening Plan and Delhi-Meerut Expressway
First two portions - Nizamuddin Bridge to UP Gate and UP Gate to Dasna - will be widened to 14 lanes include 06 lanes ( Delhi-Meerut Expressway ) at the center which is barricaded corridor for straight going traffic. The remaining portion Dasna to Hapur will be 08 lane highway.

National Highway 24 Widening Plan in Delhi, Ghaziabad and Hapur | Delhi Dasna Meerut Expressway ( Speed 120 km/h ) | 14 Lane with Cycle Track on Both Side | 6 Lane Expressway in Middle | 4 - 4 Lane Normal Highway on Both Side | 2.5 Meter Cycle Track and Foot Path on Both Side | Include Bridge, Flyover, Vehicular Underpass, Railway Bridge, Foot Underpass, Foot Over Bridge

NH 24 Widening | Delhi Meerut Expressway Completion Date
From Sarai Kale Khan in Delhi to UP Gate on NH 24: Scheduled to complete on 26 May 2019 but we will finish it by January 2018 (said by NHAI)
From UP Gate to Dasna: Complete in 2020 but again this one too will accomplish by February 2019.
From Dasna to Hapur: Complete on June 2018 well before the scheduled date.
From Dasna to Meerut: If all goes well, the work will start only in March 2018 and will complete in at least two years, i.e. by 2020.

NH-24 Widening Design and Plan | Contains Four Package
Nizamuddin Bridge to Delhi-UP Border 8.7 KM Long, 14 Lane ( 6 Lane Expressway, 8 Lane Normal Highway, 2.5 Bicycle Track on Both Side ) 4 Flyover 3 Vehicle Underpass
Delhi-UP Border to Dasna 19.2 KM Long, 14 Lane ( 6 Lane Expressway, 8 Lane Normal Highway, 2.5 Bicycle Track on Both Side  ) 15 Vehicle Underpass 6 Foot Underpass 1 Flyover
Dasna to Hapur 22.2 KM Long, 8 Lane Normal Highway (Previously it was 6 lane but in Sep-Oct 2016 Board Meeting It Update to 8 Lanes) 1 Flyover 12 Underpass
Dasna to Meerut 46 KM Long, 6 Lane Expressway ( Greenfield Alignment)

NH 24 Widening Update Status and Latest News 2017

Update on 04th October 2017: 7 Vehicle Underpass between Khora to Chhajarasi Hindon, 3 ramp will be available to climb the highway (UP Gate, ABES Cut and Lal Kuan), Existing flyovers of Lal kuan on NH91 will be broken.
Update on 28th June 2017: News About UP Gate to Dasna NH24 Widening: The plan was amended to 15 underpasses and a just one flyover, at Lal Kuan. Officials said the underpasses will be constructed in a 'staggered' manner along the highway at locations between successive T-points. Work on the second phase, up to Dasna, will begin on August 1. The new highway should be ready by March 2020. Five lanes each will be added to each side of the existing highway before construction work begins on the main carriageway so that traffic is not disturbed.
Update on 13 June 2017: According to the NHAI, the traffic volume is going to double once the work on Delhi-Meerut expressway is complete. Delhi government's PWD has revived the project for constructing a 2.5km-long tunnel between NH-24 and Lodhi Road
Update on 02 May 2017: NHAI will use Gazipur solid waste in NH 24 widening and Delhi-Meerut Expressway. Flyover at CISF cut is canceled as Delhi Metro will extend to Indirapuram, New Flyover at Lal Kuan Ghaziabad, 13 Vehicle underpass 30 meters wide (UP Border to Dasna), 12 Foot underpass 20 meters wide (UP Border to Dasna)

NH-24 Widening Work Tender Company and Cost
Package-1 Welspun Enterprises ( company from Gujarat ) won 8.7 KM long  Nizamuddin Bridge Delhi to UP border widening project, its cost Rs937 crore
Package-2 widening of Delhi-UP border to Dasna (19.2 KM long) Tender goes to Apco Chetak (Apco Infratech is based in MP and Chetak Enterprises in Rajasthan), its cost Rs1998 crore ( Cost of shifting of transmission lines: Rs 225 crores, Cost of shifting water pipeline: Rs 160 crores, 22,027 trees will cut and 22 crores compensation given to district forest department )
Package-3 from Dasna to Hapur 22.2 KM long, had been awarded to a company called Apco Chetak (Apco Infratech is based in MP and Chetak Enterprises in Rajasthan), its cost Rs1,098 crore.
Package-4 The greenfield package 46 KM from Dasna to Meerut requires land acquisition and work is in progress. “As soon as govt. get 80% of the land, the tender will out", project cost Rs3,588 crore.

Electronic Toll Collection (ETC) system will be installed on barricaded stretch, which is part of Meerut expressway and the design speed will be 120 kmph. Other eight lanes - four on each side - would be a normal highway and commuters won't have to pay the toll.


From nhai.org tender link
Development of Delhi-Meerut Expressway from Km 0.000 to Km 27.500 including 6/8 Laning of NH-24 from Km 0.000 to Km. 49.346 (Hapur Bypass) in the State of Delhi and Uttar Pradesh- Package –I- from Km 0.000 to existing Km 8.360 in the State of Delhi - on Hybrid Annuity Mode.

Current Situation of NH 24 Traffic >> https://www.youtube.com/watch?v=VZH-AIZjtRY

6 comments:

  1. kab tak hoga...10 years or may be more

    ReplyDelete
  2. Meerut Delhi expressway ke saath Meerut Bulandshahr road ka bhi udghatan hua tha. Jiska tender bhi ho Chuka hai Lekin Kaam shuru nahi hua kyonki Abhi tak nhai ne farmers Ko payment nahi ki hai. Bus ribbon Kato karo kuch nahi

    ReplyDelete
  3. Sir, ye Delhi - Meerut Expressway (PKG-2) kab start hoga ?

    ReplyDelete
  4. It's going to be crucial that the project will complete on time. Tender of Dasna to Meerut express way has been cancelled and it is not reissue for the past 1 and a half month

    ReplyDelete
  5. Choro ki sarkar neta ki jai jaikar

    ReplyDelete